LIST OF PROJECTS DONE BY JTP CONSULTING ENGINNERS

TO OVERSEAS PROJECTS / CLIENTS

 PROJECT LOCATION CLIENT PERIOD DESCRIPTION   BUILT UP AREA IN SQ.M
1.Refinery Building Development: Main building Canteen/ Dining Block MosqueMesaieed QatarQatar Design Consortium & Qatar PetroleumNov’ 02 to March’ 03G + 10 G + 1   G + 1 BS Standards  15000 25000   400
2.Aljazi TowerDoha, QatarQatar Design Consortium & Aljazi Real Estates    Oct’ 022B+ G + 20 BS Standards  30000
3.ALBA- RODDING SHOPBahrainBECHTEL / L&T  Aug ’03 to Feb ‘04  SHOP BLDG, G + 1-Steel +RC structure BS Standards 1200MT10,000      
4.Lafarge Cements  BangladeshLafarge& L&T Romboll  Oct ’03 to Dec‘03  General Cargo Jetty         
5.B+M+G+6 Shop& Apartments at Bin MahmoudQatarQatar Design Consortium/MR investmentsFeb ‘04B+G+6 BS Standards  7600
6.G+5 Apartments at Mansoura  QatarQatar Design ConsortiumMar ‘04G+5 BS Standards  4000
7.B+G+5 Apartments At Bin Mahmoud For SHK. Khalid Bin Abdul Rahman AlthaniQatarQatar Design ConsortiumApril ‘04G+5 BS Standards  4000
8PreGrinder Mill building And Cement Transport SystemKuwaitKCC-Kuwait / Ultra Tech Cement Ltd,Mumbai, IndiaJune ‘041600 MT. AISC , ACI Standards 45m high 36mX36m. Retrofit of conveyor Gallery 
  9.  Lafarge Cements – Nine no. of Transfer Towers    BangladeshLafarge& L&T ECCD  June ‘04 To Nov ‘04500 MTAISC stds
10COAL MILL BLDGKuwaitKCC2004RETROFIT OF STEEL BLDGAISC stds
11National Housing corporation-Sri Lanka – 12 Storied  buildingColomboGraffiti Architects Pvt.Ltd, Chennai G+11 BS Standards  11,000
12Doha south sewageDoha QatarDrainage affairs, Doha,ITT Sanitaire UK +TCC/CCC and QDC ,QatarMar ’05 to June’05BS Standards  From Inlet works to Sludge thickener building covering all buildings and structures.
    13          SEA WATER TREATMENT PLANTMAESAID IN QATAR1000 MW POWER PLANT-QEWCNOV’07BS Standards  ALL CIVIL WORKS
14  Benu Cements close circuiting the cement millsNigeriaSabash Engineers ChennaiAPRIL’08BS Standards   
15PET COKE STORAGE SHED AND 2x 15000 MT STORAGE SILOS 2NOSKUWAIT    PCICJULY 2011-2012AMERICAN STANDARDSALL CIVIL AND STRUCTURAL WORKS 200X65M shed AND 28M DIA X60M SILOS
16Waste Water Treatment WorksIRAN AUG-11BS 8007/8110ALL TANKS AND PROCESS BUILDING
17Cement Plant for FCKSAngolaETA STAR International2013AmericanSilo checking, PH building roof checking ,Non Plant buildings
18Maintenance Shed cum workshop buildingKuwaitPCIC2013AmericanTotal consultancy
19FACILITIES BUILDINGOMANGEC2014BRITISHFive BUILDINGS Steel+RCC
20BUILDINGS FOR CLINKER GRINDING UNIT  KUWAITFLSMIDTH, Chennai2015BRITISHDUMP  HOPPERS, TUNNELS, TTs, Conv..GALLER IES,PACKING AND LOADING PLANT ,hopper building. SUBSTATIONS
21Sea water Intake StructuresUAEWORLEY Parsn ,Chennai British 

INDIAN PROJECTS / CLIENTS :-   ( Several Local commercial works not Listed )

  PROJECT LOCATION CLIENT ARCHITECT/ CONSULTANT NO.OF FLOORS And Descrip-tion BUILT UPAREA in Sq.ft
1         2       3Wagon Tippler Building     KILPAUK-WTP- CENTRIFUGE HOUSE     Tiruppur Water Supply Project      Jharsugu da       CHENNAI       Tiruppur- TamilnaduL&T ECCG. For L&T Cements JCW plant     L&T ECCG.       L&T ECCG.ANNA UNIVERSITY     GKW Consult         GKW consultThree nos Ground level reservoirs & pump houses 2 ML to 6.5 ML capacity         
43 nos 132/33 kv Switch yardsTISCO-JamshedpurL&T ECCG.MN Dastur & companySeveral Gantry+ tower structure equipment supports with sub structures. 
  5  Apartments at West KK Nagar            Chennai  Mr.Ashokan  Five Storied RC building  20,000
  6    Tensile Roof -EBEN IT park Mauritius        MIT.LTD  L&T ECCG    TCE  & DALAL    
7      Switch yard Structures for APTRANSCOAndhra-PradeshL&T ECCD   
  8    RC Water Tank tower & UG SumpCalicut Airport AuthorityL&T ECCDIIT Madras  
  9NEW TERMINAL BUILDINGCalicut Airport AuthorityL&T ECCDIIT Madras  
    10GUEST HOUSES  UTCL    G+1 
  11CONTROL BUILDING(SUBSTATION,400 MW)  KONASEEMA  L&T ECCD ,EIL Delhi  NTPC,DELHI  G+2       
  12Fly Ash Bucket elevator Building    Hirmi Cement worksUltra Tech Cement Ltd,Mumbai, India  75MT 
  13Kiln Maintence support towers-PortableAt Four cement plantsUltra Tech Cement Ltd,Mumbai, India  30MTFor tyre replacement  
  14GARMENT FACTORY  Maduravoil, Chennai  Graffiti Architects Pvt.Ltd Three Storied 50’ Span RC45,000
  15Raw Meal Belt Bucket elevator Structure    Hirmi Cement works  Ultra Tech Cement Ltd,Mumbai, India  100MT 100m high 
16Earth Quake Resistant Apartments  Virugambakm -ChennaiM/S Ravi chandran &Co G+1 Five Types Stils +3 –Two blocks40,000
  172Nos Apartments  7th and 12th Avenues Ashok Nagar, ChennaiM/S Ashok Foundations G+320,000
  19    5000 MT clinker storage and unloading bunkers and Wagon Loading Bldg      Hirmi Cement works  Ultra Tech Cement Ltd. Steel hoppers ,RCC walls & RC Framed building.completed
  20Close Circuting of Mill 1,2,3 Awarpur    Awarpur Cement Works  Ultra Tech Cement Ltd. RC Framed structure supporting Sepax separators and Retrofitting Structures  completed
21Coal Handling SystemHirmi Cement WorksUltra Tech Cement Ltd. Conveyor Galleries, Trestles, Crusher house etc.completed
22Wagon loading BuildingJharsuguda Cement WorksUltra Tech Cement Ltd. 350m long Shed and precast platformcompleted
  23Retrofitting ESP supporting structuresAwarpur Cement Works  Ultra Tech Cement Ltd  completed
24Installing two number Beumer Clinker carrying DPCsAwarpur Cement WorksUltra Tech Cement Ltd. Gallery with free end drive platform and pendulam supports   
  2540m Span GYPSUM STORAGE SHED    WBCW  Ultra Tech Cement Ltd.   Steel truss roof shedcompleted
  26      IT PARK  HYDERABAD  DKK HOSPITALITY   1.1LAC SQ.FT  completed
27    IT PARKOMR, CHENNAIAEB ENGINEERS 30,000 SQ.FTcompleted
289 MW Biomass Power Plant -Complete  INDIA-NAGPURShriram EPC -CHENNAI     All buildingscompleted
2912 MW Biomass Power plant-Complete  Chattisgarh-INDIAShriram EPC -CHENNAI         All buildingscompleted
309 MW Biomass Power plant -Complete  Tamilnadu-INDIAShriram EPC -CHENNAI All buildingscompleted
  31PREHEATER BUILDING-ADDITION OF 5TH CYCLONE      INDIA CEMENTS- Shankar Nagar, TamilNadu        ICL-Chennai   existing PREHEATER building for the additional loads  completed
    322000Mt-Cement silo+ related compressor bldg & SUBSTATION bldg    Narmada cements-             Completed
33Clinker Silo- 15,000 Mt Cement Silo- 6000 Mt Flyash Steel silo-1000 Mt & VRPM buildingMadras Cements Salem Grinding unitStephen & Associates  Completed
  34CEMENT TRANSPORT SYSTEM. 100M high New steel TOWER and  50m steel tower modificationULTRA TECH GUJARAT  Completed
352000TPD CEMENT PLANT( with 4000tpd future provisions)CKORAMANDAL CEMENTS, NALGONDA AP.ALL  major BUILDINGSSABASH ENGINEERS PVT. LTD   Completed
36L&T SHIPYARDKattupalli, CHENNAIAll land side port Buildings And major shop building   40m high framed building with 200tons crane.L&T Infra and L&T RombollONE LAC SQM          Done    
371200 TPD cement PLANT.Dandapani (Mauruthi) Cements,TrichyALL BUILDINGS AND STRUCTURESabash Engineers, Chennai DESIGN Completed
  38CM Separator building and LS crusher building  Bagolgot Cements and Industries LTD Sabash Engineers, Chennai Done
39Coal Mill Dynamic Separator Installation works & Raw Coal Storage Shed 70x120mAwarpur Ultra Tech   Done
40New Clinker line – abt 400m long with a Transfer tower supporting bins and BEsGujarat Cement works   Completed  
41Cement Transport line to Jetty- Modification to suit siteGujarat Cement works   Completed  
42Raw mill Roller removing EOT Supports , DPC modification, 100t Bin structure, New Guest HouseNarmada Cements     Design completed
  43New Packing Plant ,Truck loading & Cement Bulk Loading bldgJharsuguda Ultra Tech     Completed  
  44Wagon Loading Bldg  Jharsuguda Ultra Tech    750m, 2000tons. 22 loading conveyors  Completed  
  45Marriage hall and Three star Hotel building at Sirkali  TERN    LArge span four storey RCC bldg  60000 sq ft
    46Lime Stone and Coal Storage Shed Structures Proof checkingUltraTech ,Rawan, CHATTISGARG    90m and 55m single span 200m Long buildingsCompleted
    47COAL HANDLING PLANT for COAL INDIA MCL-Anantha CHP  SHIVANI-Oil Exploration services    Two Silos 5000t capacity, Semi ground Bunker 15000MT capacity 12m/10m wide  4000TPH conveyor Galleries  Completed  
48Packing Plant and truck loading Terminal at Nagerkoil – TamilnaduChettinad Cements  Steel building Housing 1000Tx2 Silo and ,PackerCompleted  
49TRUCK LOADING BUILDING AND HOPPER BUILDING  UTCL- PATNA GRINDING UNIT  Hopper STEEL BUILDING 500MT      Completed  
50Alternate Fuel SystemsUTCL-Gujarat    STEEL BUILDINGS, Conveyor Gallery  Completed  
51RSPL -COAL HANDLINGGUJARATHFLSMIDTH 2500 MTCompleted  
52Ultra Tech-Awarpur   FLSMIDTH   Preheater Building (Only RC Floors and Platforms)  DONE  
53CEMENT PLANTS IN NEPAL FLSMIDTH ALL PLANT BUILDINGSDONE  
54PREMIER CEMENT PLANTS IN BANGLADESH FLSMIDTH CEMENT MILL AND MILL HOPPER BUILDING AND TRANSPORT TO SILODONE  
55NCTPP-TANGENCO   POWER PROJECTCHENNAIBGR ENERGY 14-TRANSFER TOWERS WITH CIVIL SUBSTRUCTURE, 6 RCC BUILDINGS LIKE SUBSTATIONS, COMPRESSOR HOUSE,ELECTRO CHOLRINATION,CHEMICAL HOUSE,OIL UNLOADING PUMP ROOM ETC.,PIPE RACKSDONE                    
56Chettinadu-PortMangalore TerminalESSAE 1600MT Cap rectangular STEEL Surge BIN, and 130 tons Weigh Bin-One of Its Kind BuildingDone
57JSW-TORNAKALKARNATAKA) 6X1400MT STEEL BINS AND BUILDING,   CROSS COUNTRY PIPE CONVEYOR DESIGN CHECKINGDONE
5817 KMs CROSS COUNTRY PIPE CONVEYOR AND RELATED STRUCTURESMAHAGENCO-NAGPURISJEC(IJT-THOMPSON)DCPL5500MT STEEL   25000CUM RCC. ALL STRUCTURESONGOING

Completed 3 Nos 5 MLD STPs for TWAD board, TamilNadu, 50MLD STP for L&T ,37 MLD WTP in MIZORAM, 138 MLD STP for TATA PROJECTS UJJAIN , Filter Building for TWAD, RSGF Filter bldg. for 500MW Power Plants of NTPC(BGR), etc.

SEVERAL MINOR STRUCTRURAL WORKS/RETROFITS NOT LISTED.